Project Schedule for 2006:

    1.0 - CIRCULATION PLAN -
    1. Mapping: June and July
    2. Multimodal Framework: June and July
    3. Development Summary: June and July
    4. Traffic Demand: June and July
    5. Traveler Safety: June and July
    6. Agriculture, Freight, and Delivery: June and July
    7. Transportation Alternatives: early June – late August
    8. Draft Circulation Plan: early June – late September
    9. Prioritized Action Plan: August – late September
    10. Funding Element: August – late September
    11. Final Circulation Plan: August – late September
    2.0 - PUBLIC EMPOWERMENT-
    1. Project Advisory Committee: Meetings are tentatively scheduled for the second week in
      June, July, and August, and the third week in September and October.
    2. Public Workshops: Workshops are tentatively scheduled for the second week in
      June and August, and the third week in September.
    3. Project Website: Mid June – November
    4. Other Information: Mid June – November
    3.0 - PRESENTATION TO COUTY-
    1. County Planning Commission: Week of October 15 – 21
    2. County Council: Week of November 19 – 25
    4.0 - PROJECT MANAGEMENT
    • June-November
    5.0 - FIELD PRESENCE
    • June 11th-17th
    • July 9th-15th
    • August 6th-12th *
    • September 17th-23rd *
    • October 15th-21st *
    • November 12th-18th *
      (* indicates tentative dates)

Charlier Associates, Inc.
Project Schedule 2005
- View PDF (94KB)