Project Schedule for 2006:
1.0 - CIRCULATION PLAN -
- Mapping: June and July
- Multimodal Framework: June and July
- Development Summary: June and July
- Traffic Demand: June and July
- Traveler Safety: June and July
- Agriculture, Freight, and Delivery: June and July
- Transportation Alternatives: early June – late August
- Draft Circulation Plan: early June – late September
- Prioritized Action Plan: August – late September
- Funding Element: August – late September
- Final Circulation Plan: August – late September
2.0 - PUBLIC EMPOWERMENT-
- Project Advisory Committee: Meetings are tentatively scheduled for the second week in
June, July, and August, and the third week in September and October.
- Public Workshops: Workshops are tentatively scheduled for the second week in
June and August, and the third week in September.
- Project Website: Mid June – November
- Other Information: Mid June – November
3.0 - PRESENTATION TO COUTY-
- County Planning Commission: Week of October 15 – 21
- County Council: Week of November 19 – 25
4.0 - PROJECT MANAGEMENT
5.0 - FIELD PRESENCE
- June 11th-17th
- July 9th-15th
- August 6th-12th *
- September 17th-23rd *
- October 15th-21st *
- November 12th-18th *
(* indicates tentative dates)
Charlier Associates, Inc.
Project Schedule 2005 - View PDF (94KB)
|